How Agencies Can Measure Project Profitability
Busy agencies can still lose money on projects. A practical way to track income, direct costs and team time per project or client — without complex software.
In this article
- What project profitability means
- Step 1: Record income and direct costs per client
- Step 2: Estimate team time
- Step 3: Calculate an internal hourly cost
- Step 4: Put it together
- What to do with the results
- Keeping the books clean
- FAQ
- Do I need time tracking software?
- Should overhead be included in project costs?
- What's a healthy project margin?
Digital agencies, software houses, event companies and consultancies often feel busy and still struggle with cash. The usual reason: some projects quietly lose money, and nobody notices because income and costs are only looked at in total.
What project profitability means
Project profit = Project income − Direct project costs − Share of team time
- Project income: what the client pays for the project.
- Direct costs: freelancers, paid tools or assets, printing, travel, ads spent on the client's behalf.
- Team time: hours your salaried staff spent, at an internal cost rate.
Step 1: Record income and direct costs per client
Add each client as a party and record every payment received against them. Record direct costs with the client name in the description (and, if the cost is paid to a freelancer, add the freelancer as a party too).
The client-wise report gives total income per client. Direct costs per client come from filtering entries by description or by using a purpose per major cost type.
Step 2: Estimate team time
You don't need time-tracking software to start. At the end of each week, ask each team member to estimate hours per project in a simple sheet:
| Person | Project A | Project B | Retainer C | Internal |
|---|---|---|---|---|
| Designer | 14 | 10 | 6 | 10 |
| Developer | 22 | 8 | 4 | 6 |
Step 3: Calculate an internal hourly cost
Hourly cost ≈ (monthly salary + share of overhead) ÷ productive hours.
Example: a developer earning ৳ 60,000, overhead share ৳ 20,000, 120 productive hours → ৳ 667/hour.
Step 4: Put it together
Project A — company website
| ৳ | |
|---|---|
| Income (2 instalments) | 3,00,000 |
| Freelance illustrator | (35,000) |
| Premium theme & plugins | (12,000) |
| Team time: designer 40h × ৳ 500 | (20,000) |
| Team time: developer 90h × ৳ 667 | (60,000) |
| Project profit | 1,73,000 (58%) |
Retainer C — social media
| ৳ | |
|---|---|
| Income (3 months) | 1,20,000 |
| Ad design freelancer | (30,000) |
| Team time: 150h total at ৳ 550 | (82,500) |
| Project profit | 7,500 (6%) |
Retainer C looked fine on the invoice, but it barely covers costs. Options: raise the fee, reduce scope or improve the process.
What to do with the results
- Price new projects using real hours and costs — see pricing freelance services.
- Renegotiate or drop chronically unprofitable clients.
- Collect faster — agencies often finance clients unknowingly. See getting paid on time.
- Watch scope creep: compare estimated vs actual hours on every project.
Keeping the books clean
Agency-wide numbers still matter: monthly profit and loss, cash flow and salaries as a percentage of income. Averiq gives you client-wise income, employee-wise payouts and purpose-wise costs as PDF or CSV — export to a spreadsheet for the time-cost calculation. For a separate view of big projects, some agencies even create one organization per major project.
FAQ
Do I need time tracking software?
Not to start. Weekly estimates are enough to reveal unprofitable projects. Precise tracking helps later.
Should overhead be included in project costs?
Include it in the hourly cost rate, so every project carries its fair share of rent, tools and admin.
What's a healthy project margin?
It varies by service. Track your own average and focus on projects far below it.
Cash book, bank & bKash accounts, profit & loss and A4 PDF reports. No credit card needed.
Create free accountKeep reading
Getting Paid on Time: Invoicing and Payment Follow-up Tips
Late payments strangle small businesses and freelancers. Practical ways to set terms, invoice clearly, follow up politely and record payments as they arrive.
How to Price Your Freelance Services Using Your Real Costs
Stop guessing your rates. Calculate a minimum hourly rate from your income goal, costs, taxes and unbillable time — then price projects with confidence.
How to Track Upwork, Fiverr and Payoneer Income Properly
Platform balances, withdrawals, fees and conversion rates make freelance income confusing. A clean method to track it from client to bank account.