How Agencies Can Measure Project Profitability

Busy agencies can still lose money on projects. A practical way to track income, direct costs and team time per project or client — without complex software.

AAveriq Team
3 min read
In this article
  1. What project profitability means
  2. Step 1: Record income and direct costs per client
  3. Step 2: Estimate team time
  4. Step 3: Calculate an internal hourly cost
  5. Step 4: Put it together
  6. What to do with the results
  7. Keeping the books clean
  8. FAQ
  9. Do I need time tracking software?
  10. Should overhead be included in project costs?
  11. What's a healthy project margin?

Digital agencies, software houses, event companies and consultancies often feel busy and still struggle with cash. The usual reason: some projects quietly lose money, and nobody notices because income and costs are only looked at in total.

What project profitability means

Project profit = Project income − Direct project costs − Share of team time

  • Project income: what the client pays for the project.
  • Direct costs: freelancers, paid tools or assets, printing, travel, ads spent on the client's behalf.
  • Team time: hours your salaried staff spent, at an internal cost rate.

Step 1: Record income and direct costs per client

Add each client as a party and record every payment received against them. Record direct costs with the client name in the description (and, if the cost is paid to a freelancer, add the freelancer as a party too).

The client-wise report gives total income per client. Direct costs per client come from filtering entries by description or by using a purpose per major cost type.

Step 2: Estimate team time

You don't need time-tracking software to start. At the end of each week, ask each team member to estimate hours per project in a simple sheet:

PersonProject AProject BRetainer CInternal
Designer1410610
Developer22846

Step 3: Calculate an internal hourly cost

Hourly cost ≈ (monthly salary + share of overhead) ÷ productive hours.

Example: a developer earning ৳ 60,000, overhead share ৳ 20,000, 120 productive hours → ৳ 667/hour.

Step 4: Put it together

Project A — company website

৳
Income (2 instalments)3,00,000
Freelance illustrator(35,000)
Premium theme & plugins(12,000)
Team time: designer 40h × ৳ 500(20,000)
Team time: developer 90h × ৳ 667(60,000)
Project profit1,73,000 (58%)

Retainer C — social media

৳
Income (3 months)1,20,000
Ad design freelancer(30,000)
Team time: 150h total at ৳ 550(82,500)
Project profit7,500 (6%)

Retainer C looked fine on the invoice, but it barely covers costs. Options: raise the fee, reduce scope or improve the process.

What to do with the results

  • Price new projects using real hours and costs — see pricing freelance services.
  • Renegotiate or drop chronically unprofitable clients.
  • Collect faster — agencies often finance clients unknowingly. See getting paid on time.
  • Watch scope creep: compare estimated vs actual hours on every project.

Keeping the books clean

Agency-wide numbers still matter: monthly profit and loss, cash flow and salaries as a percentage of income. Averiq gives you client-wise income, employee-wise payouts and purpose-wise costs as PDF or CSV — export to a spreadsheet for the time-cost calculation. For a separate view of big projects, some agencies even create one organization per major project.

FAQ

Do I need time tracking software?

Not to start. Weekly estimates are enough to reveal unprofitable projects. Precise tracking helps later.

Should overhead be included in project costs?

Include it in the hourly cost rate, so every project carries its fair share of rent, tools and admin.

What's a healthy project margin?

It varies by service. Track your own average and focus on projects far below it.